The TAC Tracker
Arlington’s Transportation Advisory Committee is a group of volunteers who study street safety requests: a crosswalk drivers can’t see, a corner where cars won’t stop, a road where they go too fast. TAC sends its recommendation to the Select Board. If the Board approves, town staff order the signs, paint the lines or plan the construction.
I wanted to know how long each of those steps takes. Here are the 28 recommendations TAC brought to the Board from June 2021 through June 2026, and what I could find about when each one was done.
Every recommendation, start to finish
One row for each, in the order the Board voted. The dashed line is today. Hover over a row for the details.
What I found
- The Select Board isn’t the bottleneck. Half of TAC’s memos reach a vote within five weeks. A few sat for months: Downing Square’s signs waited five and a half months, North Union St five and a half and Winter St six.
- Speed limits moved fastest. Arlington rescinded every special speed limit above 25 mph and set up five 20 mph safety zones in under two years. Four of the zones have a record of their signs going up, each within about eight months of the vote. TAC wrote these memos to a template, the state had a set procedure, and the work was all signs.
- Small spot fixes leave no trace. Thirteen recommendations the Board approved or accepted have no record of being done. Eight of them are more than two years old, and most of those are a few signs or some paint. Some are surely done. Nobody wrote down when.
- Anything with a beacon or a curb takes years. The flashing beacons at Summer St and Victoria Rd were approved on January 23, 2023 and went in during August 2026, once a state grant paid for them. Chestnut St took a little over two years.
The list
Every date, with the memo, the vote and the record that it was done.
Sources and limits
- The recommendations are every TAC memo that reached a Select Board agenda from 2021 through June 2026, from the Board’s agenda packets and minutes. I left out TAC appointments, its general updates and its follow-up speed studies. Where one memo held several requests, like the four on October 24, 2022, each gets a row.
- The request date is the Select Board meeting where a resident’s letter was received and sent to TAC. Requests that went straight to TAC or to town staff, and work TAC started itself, have no request date.
- The TAC date is the date on the memo. The Summer St and Victoria Rd memo is dated December 14, 2021, but it says “11/20/22 Final” and the Board heard TAC voted on it in December 2022, so I used December 14, 2022.
- The second speed limit vote, on December 16, 2024, used TAC’s memo of April 10, 2024, which asked the Board to start with Broadway and Park Ave and come back for the rest. I left that planned wait out of the time from memo to vote.
- The done date comes from whatever first says the work was finished: a later Select Board packet, TAC’s recap of its speed limit work on December 4, 2025, or TAC’s own minutes, which the town has posted with the Board’s since February 2026. “By” means that’s the first mention, not the day it was built. Before 2026, TAC’s minutes are only on the town website, which I couldn’t read for this, so the done dates for older work are the most likely to be missing.
- No record yet doesn’t mean it wasn’t done. It means I haven’t found it written down. If you know when one of these went in, tell me on the Labs page.
- Chestnut St was done in two stages. The warning signs and No Turn on Red signs were up by late 2021. The curb extensions, island, beacon and bike lanes came with the repaving, nearly finished by August 14, 2023. The row ends at the second.